Actual cost was divided by earned value, producing 1.33 and a false impression of good performance. CPI is EV/AC, so the project was only at 0.75.
Inspect, commit, prove, fix, and sign off.
Follow the investigation process used in the field β in five guided steps.
Review the problem, diagram, and evidence.
Choose your hypothesis.
Run calculations and test your idea.
Select and validate a safe correction.
See the full debrief and key takeaways.
A project has BAC=$500,000, planned value PV=$240,000, earned value EV=$210,000, and actual cost AC=$280,000. Determine CPI, SPI, CV, SV, and EAC assuming current cost efficiency continues.
Find the root cause, confirm the fix, and see how this connects to the exam.
The CPI ratio was reversed.
Earned value is the numerator in both CPI and SPI.
Use standard EVM ratios and variance sign conventions.
CPI=EV/AC=210/280=0.75. SPI=EV/PV=210/240=0.875. CV=-$70,000, SV=-$30,000, and EACβ$666,667 if current CPI continues.
Use CPI=EV/AC, SPI=EV/PV, CV=EV-AC, and SV=EV-PV.
The project is earning less value per dollar spent than planned.
Each case is designed to build the judgment, analysis, and confidence you need for engineering exams β and beyond.
Basic subject familiarity helps, but every case is designed to teach through the investigation itself.
Most cases are designed for a focused 5β10 minute investigation.
Each case is mapped to a verified exam, subject, topic, and misconception before publication.
The sealed debrief unlocks with the root cause, corrected reasoning, fix, and takeaway.