A project has activities: A=3 days; B=5 after A; C=4 after A; D=6 after B; E=3 after C; F=2 after both D and E. Determine project duration, critical path, and total float on the C-E branch.
Find the root cause, confirm the fix, and see how this connects to the exam.
The shorter parallel branch was treated as project duration.
The merge activity waits for all predecessors.
Use forward/backward passes and identify the zero-float critical path.
A-B-D-F takes 3+5+6+2=16 days. A-C-E-F takes 12 days, so the project duration is 16 days and the shorter branch has 4 days of float.
Perform a forward pass and use the longest zero-float path as the project duration.
The longest zero-float path through the activity network.
Each case is designed to build the judgment, analysis, and confidence you need for engineering exams β and beyond.
Basic subject familiarity helps, but every case is designed to teach through the investigation itself.
Most cases are designed for a focused 5β10 minute investigation.
Each case is mapped to a verified exam, subject, topic, and misconception before publication.
The sealed debrief unlocks with the root cause, corrected reasoning, fix, and takeaway.